$172K in additional design services sought from Dibble Engineering

An amendment to a project order with Dibble Engineering for up to $172,365 for additional design services associated with Town Center infrastructure improvements has been approved by the Queen Creek Town Council.

The council on July 15 voted unanimously to approve the change in a consent agenda with other items with Councilmember Emilena Turley absent. On the dais were Mayor Gail Barney and Councilmembers Jake Hoffman and Robin Benning. Meeting by WebEx were Vice Mayor Julia Wheatley and Councilmembers Jeff Brown and Dawn Oliphant.

Town Council, on Feb. 6, 2019, approved an on-call project order with Dibble Engineering for $394,565 to design new collector and local roadways, water mains, sanitary sewer utilities, storm-drain systems and retention basins associated with Town Center infrastructure improvements, Public Works Director Troy White said in a memo to the council.